15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

Which property do transition metals have in common?
Ocean water becomes colder; the density of ocean water increases or decreases?
(X+9)(x-2)-9x-6 equivalen to
What is the most important thing you could do to improve your health? Why?
PLEASE HELP QUICK!!!!!!!!!!!! Describe how you could calculate the actual temperature from the anomaly.
Which three logical predictions can be made after reading this passage?
John white returns to Roanoke when was that​
Engineering is a broad category that includes a variety of occupations and attempts to solve problems using math and
New York and New Jersey were originally settled by ___ settlers A. English B. French C. Dutch D. Spanish
What is the mass of a 500.00 mL sample of seawater with a density of 1.025 g/mL?